Flagship

BNS Submarine Base, Pekua

For the Bangladesh Navy at Pekua, we delivered civil works across the Fleet Headquarter, ward rooms, generator rooms, roads, prefabricated steel structures and boundary walls — and one of the most demanding jobs in the country: excavating the world's third-largest harbour basin, sized for seven submarines.

38,000 m²
Fleet HQ civil & finishing
61,000 m³
Three-layer deep excavation
3 km
Rigid-pavement road
200,000 m³
Land developed & filled
Civil works at the BNS Submarine Base, Pekua
Selected projects

A closer look at what we've delivered.

Civil works, deep excavation, roads, steel structures and land development — for the Bangladesh Navy and leading international contractors.

Fleet Headquarter — Civil, finishing, fire safety
2020–2023

Fleet Headquarter — Civil, finishing, fire safety

China Zhenjiang Int'l Economic & Technical Corp.

38,000 m² civil works, floor tile, putty & paint, false ceiling, fire-safety pipeline.

BNS Submarine Base, Pekua
Ward Room — 6-storey building & finishing
2023–2025

Ward Room — 6-storey building & finishing

Zhong Nong Construction Co. Ltd.

12,000 m² finishing — floor tile, putty & paint.

BNS Submarine Base, Pekua
Harbour Basin — Deep excavation (world's 3rd largest)
2018–2022

Harbour Basin — Deep excavation (world's 3rd largest)

BNS Pekua Project Department

600×400×18 m basin for seven submarines; ~150 pieces heavy equipment deployed.

BNS Submarine Base, Pekua
Rigid-Pavement Road — 3 km
2023–2025

Rigid-Pavement Road — 3 km

Ming Hong Shun Co. Ltd.

3 km rigid pavement, 3000 m × 4 m × 0.3 m, incl. 2000 m³ water tank.

BNS Submarine Base, Pekua
Prefabricated Steel Structure — Dry Dock management
2023–2025

Prefabricated Steel Structure — Dry Dock management

China Zhenjiang Int'l Economic & Technical Corp.

6 assemblies, ~1080 m² each; diesel & water reserve tanks.

BNS Submarine Base, Pekua
Prefabricated Diesel & Water Reserve Tanks
2023–2025

Prefabricated Diesel & Water Reserve Tanks

Sino Construction Co. Ltd.

Diesel tanks Ø18 m × 16 m shell height; 2 × 2000 m³ water tanks.

BNS Submarine Base, Pekua
Boundary & Sea-Water Protection Wall — 3 km
2021–2024

Boundary & Sea-Water Protection Wall — 3 km

Rong Tai Company Ltd.

3 km boundary wall and sea-water flow protection wall.

BNS Submarine Base, Pekua
Land Development — S. Alam Private Port
2016–2020

Land Development — S. Alam Private Port

Jaynab Builders Ltd. / Bangladesh Navy Authority

200,000 m³ sand filling and land development.

Pekua, Cox's Bazar
Deep Tube-Wells — 4" & 16" dia.
2024–2025

Deep Tube-Wells — 4" & 16" dia.

Yunnan Zhongsheng

Installation of 4-inch and 16-inch diameter tube-wells, 12 pieces.

BNS Submarine Base, Pekua
Start your project

Tell us what you're building.
We'll send a quotation.

Construction, equipment, manpower or materials — message us on WhatsApp with your requirement and site, and our team responds fast.

Request a QuotationEmail us